MIL-DTL-11891G(AT)
APPENDIX D
g.
Test environment at time of incident.
h.
Disposition of failed part. Hold and tag failed part.
i.
Test report number.
j.
Vehicle registration number.
k.
`Code/serial number identification of failed component and code/serial number of
replacement component.
l. Authorized signature.
D.3.24.1 Major track incidents. All track incidents determined to be major, that is, track
throws, misguides, etc., shall be immediately reported to AMSTA-TR-E/BFV.
D.3.25 Final report. The test site shall prepare a final technical report at the completion
of testing. The report shall include as a minimum the following:
a.
Data collected. Include copies of TIRs for track related failures.
b.
Summary of test findings.
c.
Photographs, tables, and charts to reflect test findings.
d.
If more than one contractor is attempting qualification testing at one time, test
results shall be grouped by contractor.
D.3.26 Photographic coverage. The test site shall furnish color photographic coverage of
all significant test events to include, as a minimum, track throw or misguide damage (vehicle and
track system), broken or bent center guides, sprocket damaged shoes, and broken pins,
representative sampling of pad failures, and a representative sampling of pads which have not met
the failure criteria.
D.3.26.1 Applicable information. Together with the photographic coverage, applicable
information (manufacturer, serial number, test course, mileage sustained, etc.) shall be recorded
and accompany the photographs. This data is to be included in the final report.
D.3.27 Distribution of reports. The distribution of test incident reports and final reports
shall be as specified by the Preparing Activity (see 6.2).
Custodian:
Preparing Activity:
Army - AT
Army - AT
(Project 2530-0402)
95
For Parts Inquires call Parts Hangar, Inc (727) 493-0744
© Copyright 2015 Integrated Publishing, Inc.
A Service Disabled Veteran Owned Small Business